Duggan Park Paving Overlay
Overview
City Council considered the asphalt paving overlay project during 2009 budget deliberations and has opted to undertake the local improvement project over a period of up to 3 years to ease the impact on the neighbourhood and municpl budget.
Phase 1 and 2 of this project were completed in 2009 and 2010. Phase 3 of this project is scheduled for completion for the summer of 2011. The attached plan highlights the phases of our overlay program 2009-2011.
In addition to street signage being posted to advise all residents of the limits of work to be undertaken, residents can expect a notice from Border Paving advising of the pending work on their block. Access and parking during construction (one or two days) will not be available. Please park on adjacent streets or make other arrangements as necessary. For those with unique situations contact Engineering Services, so that everything possible can be done to accommodate those affected.
The supervision of this project will be conducted by Engineering Services. For further information contact 780-672-4428 or email.
In discussions with the project contractors, a tentative construction schedule is expected to unfold as follows:
| Components of the Project |
Tentative Schedule |
Contractor |
| Utility repairs to manhole frame and covers |
Phase 1 & 2 completed in 2010
Phase 3 Spring 2011 |
Border Paving Ltd.
Camrose, Alberta
Phone: 780-672-3389 |
| Concrete curb and walk spot repairs as required. |
Phase 1 & 2 completed in 2010.
Phase 3 Spring 2011 |
Jo's Concrete Services Ltd.
Wetaskiwin, Alberta
Phone: 780-361-1180 |
| Asphalt grinding and overlay. |
Phase 1 & 2 completed in 2010.
Phase 3 Summer 2011 |
Border Paving Ltd.
Camrose, Alberta
Phone: 780-672-3389 |
| Budget and Funding |
|
The total proposed budget for this project is $1,525,000.
|
| The proposed budget for the 2009 component of this project is $500,000. $100,000 from municipal levy, $200,000 from debenture borrowing local improvement and $200,000 from Alberta Municipal Infrastructure Program. |
| The proposed bugdet for the 2010 component of this project is $525,000. $315,000 from municipal levy and $210,000 from debenture borrowing local improvement. |
| The proposed budget for the 2011 components of this project is $525,000. $315,000 from municipal levy, and $210,000 from debenture borrowing local improvement. |
|
|