50 Street Rail Trestle Construction

Overview

The City has entered into an agreement with CN Railway to replace the existing wooden underpass trestle structure on 50 Street south of 44 Avenue with a steel structure wide enough to accommodate the safe passage of single lane two way vehicle traffic under the trestle.  A pedestrian sidewalk will be provided on the west side of the roadway.

In 2009, the City replaced a section of the existing watermain, approximately 200 metres on either side of the trestle.  In conjunction with this work the roadway was lowered at the trestle to provide adequate vehicle clearance under the structure (in the order of 4.7 meters). The roadway will remain gravel base until 2010. 

 Resources 
 Bridge Cross Section
 Watermain Replacement

 Components of Project  Schedule  Contractor
Trestle Construction  To Be Completed May 2010  Under CNR Management
(Edmonton)
Watermain  Replacement  Completed October-November 2009  Alfresco Contractors Inc.
(Sherwood Park)
Roadway Gravel November 2009  Alfresco Contrctors Inc.
(Sherwood Park)

 Budget and Funding

The 2009 scope of work to be undertaken by the City of Camrose is estimated at $150,000.




Home | Accessibility | Located at: 5415 - 49 Avenue | Mailing: 5204 - 50 Avenue | Camrose, AB | T4V 0S8
Ph. (780) 672-4426 | Fx. (780) 672-2469
Copyright & Disclaimer | Condition of Use & Privacy Statement | Using Renewable Energy | Powered by CivicPlus
Click to Home