Bridge Deck Rehabilitation 44 Avenue, 47 Avenue, 54 Avenue

Overview

The City of Camrose Transportation Master Plan (2007) indentified the need for a Five Year Bridge Rehabilitation Program.  There are four bridges within the City of Camrose that have been constructed to standard Alberta Transportation designs. The bridges were built between 1974 and 1986 and are starting to show signs of  deterioration.

The scope of work for the 44 Ave bridge (west of 50 Street), 47 Avenue bridge (east of 51A Street) and 54 Avenue bride (west of 56 Street) is to replace the existing asphalt deck with a 150mm reinforced concrete slab. This repair should extend the life of the bridges by an estimated twenty years.   

The supervision of this project will be conducted by Engineering Services.  For further information contact 780-672-4428 or email.

Resources
Project Drawings - 44 Avenue Bridge, 47 Avenue Bridge and 54 Avenue Bridge

 Components of Project  Schedule Consultant    Contractor
 Concrete Replacement  Spring/Summer 2010 ISL Engineering Services &
Land Services Ltd.
Edmonton, AB
780-438-9000
Carmarck's Enterprises Ltd.
Nisku, Alberta
Phone:  780-955-5545
 Paving Overlay      Spring/Summer 2010  ISL Engineering Services &
Land Services Ltd.
Edmonton, AB
780-438-9000
Border Paving Ltd.
Camrose, Alberta
Phone:  780-672-3389
 Budget and Funding
 The total proposed budget for this project is $400,000.00. 