Main Street Lane Paving Between 48 and 49 Avenue
Overview
The City of Camrose has been resconstructing the lanes in the downtown area for the last couple of years. This Program will continue in 2011. The remaining lanes to be reconstructed are between 48 and 49 Avenue.
The design and supervision of this project will be conducted by Engineering Services. For further information contact 780-672-4428 or email
| Components of the Project |
Schedule |
Contractor |
| Salvage of existing pavement and gravel structure. |
September 2011 |
Border Paving Ltd.
Camrose, AB
Phone: 780-672-3389 |
| Lowering / upgrading of existing shallow buried facilities. |
September 2011 |
Atco Gas |
Excavation of the road base tio provide for the placement
of granular structure. Placing of granular base material
and asphalt paving. |
September 2011 |
Border Paving Ltd.
Camrose, AB
Phone: 780-672-3389 |
| Budget and Funding |
| The total proposed budget for this 2011 component of this project is $365,000. $125,000 from Current Revenue and $240,000 from Local Improvements. |