Duggan Park Paving Overlay Phase 3
Overview

Phase 1 and 2 of this project were completed in 2009 and 2010.  Phase 3 of this project is scheduled for 2011. 

In addition to street signage being posted to advise all residents of the limits of work to be undertaken, residents can expect a notice from the contractor advising of the pending work on their block.  Access and parking during construction, one or two days, will not be available.  Please park on adjacent streets or make other arrangements as necessary.  For those with unique situations contact Engineering Services.

The supervision of this project will be conducted by Engineering Services.  For further information contact 780-672-4428 or email.

Resources
Plan of Overall Scope of Asphaltic Paving Phases 1, 2, and 3

 Components of Project  Schedule  Contractor
 Utility repairs to manhole frames and covers.  Summer 2011  Border Paving Ltd.
Camrose, Alberta
Phone:  780-672-3389
 Concrete curb and walk spot repairs as required.  Summer 2011  Jo's Concrete Services Ltd.
Wetaskiwin, Alberta
Phone:  780-361-1180
 Asphalt grinding and overlay.  Commencing August 24, 2011  Border Paving Ltd.
Camrose, Alberta
Phone:  780-6752-3389

 Budget and Funding
The proposed budget for the 2011 components of this project is $525,000. $315,000 from municipal levy, and $210,000 from debenture borrowing local improvement.